Skip to main content

Redevelopment works at the Brucity area

Redevelopment works at the Brucity area

The project consists of the redesign of the area around the new Brucity building (Hallenstraat, Zwarte Lievevrouwstraat, Visverkopersstraat, Augustijnenstraat, and parts of Kiekenmarkt, Lakensestraat, Sint-Katelijneplein, and Bisschopsstraat) with the aim of better connecting the different neighbourhoods and creating a homogeneous whole. 

The entire project will take 1.5 years. These works are divided into several phases:

Presentation of the Brucity surroundings yard (7.16 MB)

Next stages of the works

The redevelopment works are continuing. Below you will find the next stages of the project, also shown on the plan:

Brucity surroundings yard (410.62 KB)

 

 

Van Artevelde-Chartreux crossroads yard (from 5 to 30 August 2024)

  • Rue Van Artevelde and Chartreux at a dead end
  • Bus routes diverted. More info: External siteSTIB

Rue de l'Évêque works

Phase 1: from 5 August to mid-November 2024

  • Traffic maintained
  • Évêque car park inaccessible for 6 weeks
  • STIB stop moved beyond Boulevard Anspach

Phase 2: from mid-November to end 2024

  • No impact on traffic
  • Traffic maintained
  • STIB stop moved beyond Boulevard Anspach

Two days of asphalting works (Van Artevelde, Poissonniers, Vierge Noire, Laeken axis)

  • Tuesday 27 August: Van Artevelde-Melsens axis closed
  • Wednesday 28 August: Melsens-Laeken axis closed

From 1 September 2024, the Van Artevelde, Poissonniers, Vierge Noire, Laeken axis will reopen to all traffic.

The STIB and De Lijn lines will resume their route prior to the works.

Yard phases

Presentation of the Brucity surroundings yard (7.16 MB)

Project

Around Brucity

Contact

julien.mille@brucity.be

Created on 11/01/2023 (Modified on 07/08/2024)