Rempart des Moines reconstruction works

The reconstruction works at the Rempart des Moines (Papenvest) and surroundings will start on 4 February 2019. These works should be completed by the end of September 2019.

These works include the reconstruction of the footpath and the road. They will take place in 3 successive phases and require the closure of the road for car traffic:

  • The 1st phase concerns the Rue du Grand Serment, which will be closed from 11 February 2019 to 1 May 2019.
  • The 2nd phase concerns the Square Jacques Brel and the Rue des Rempart des Moines from the Rue Antoine Dansaert to the Rue du Houblon in May and June 2019.
  • The 3rd phase will be at the crossroads of the Rue du Grand Serment/Rue du Houblon in August and September 2019.

More information on the works and accessibility:

Contact:

Created on 16/01/2019 (modified on 31/01/2019)