Works at the Boulevard Clovis
On Monday 10 October 2022, the redevelopment works at the Boulevard Clovis (Clovislaan) started. These works are divided into 3 phases and last a total of 1.5 years.
Phase 1: between the Rue de Gravelines and the Square Ambiorix
Start: from 10 October 2022
Duration: 100 working days
During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.
Phase 2: between the Rue de Gravelines and the Chaussée de Louvain
Start: from 1 June 2023
Duration: 100 working days
During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.
Phase 3: intersection of the Rue de Gravelines and Boulevard Clovis
Start: during the works of phase 2
Duration: 50 working days
During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.
Redevelopment project
More info about the project:
Boulevard Clovis redevelopment