Works at the Boulevard Clovis

On Monday 10 October 2022, the redevelopment works at the Boulevard Clovis (Clovislaan) will start. These works will be divided into 3 phases and will last a total of 1.5 years.

Phase 1: between the Rue de Gravelines and the Square Ambiorix

Start: from 10 October 2022

Duration: 100 working days

During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.

Phase 2: between the Rue de Gravelines and the Chaussée de Louvain

Start: after completion of phase 1

Duration: 100 working days

During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.

Phase 3: intersection of the Rue de Gravelines and Boulevard Clovis

Start: during the works of phase 2

Duration: 50 working days

During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.