Works at the Boulevard Clovis

On Monday 10 October 2022, the redevelopment works at the Boulevard Clovis (Clovislaan) started. These works are divided into 3 phases and last a total of 1.5 years.

Phase 1: between the Rue de Gravelines and the Square Ambiorix

Start: from 10 October 2022

Duration: 100 working days

During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.

Phase 2: between the Rue de Gravelines and the Chaussée de Louvain

Start: from 1 June 2023

Duration: 100 working days

During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.

Phase 3: intersection of the Rue de Gravelines and Boulevard Clovis

Start: during the works of phase 2

Duration: 50 working days

During the works, this area is only accessible to pedestrians, cyclists, people with reduced mobility and emergency services. The rest of the boulevard remains accessible.

Redevelopment project

More info about the project:

Boulevard Clovis redevelopment

Phases of the Boulevard Clovis works

Created on 22/09/2022 (modified on 25/05/2023)
Works at the Boulevard Clovis