Works at the Rue Dansaert

Around the first half of March 2022, Sibelga works will start at the Rue Antoine Dansaert.

Phases of the yard

  • Block 1: about 280m, 12 days of trenching
  • Block 2: about 310m, 19 days of trenching
  • Block 3: about 430m, 20 days of trenching

To these blocks are added the openings for pulling cables, making connections and works at the water supply (Vivaqua).

Once the placement is complete, the connections can begin, depending on the availability of the teams, residents and merchants.

Phases of works Rue Dansaert

Accessibility

Throughout the construction period, access to shops and homes will be maintained.

There will be a temporary delivery area at each end of the yard.