Works at the Rue Reper-Vreven and Place Marsupilami

From 19 April 2022, the works to create the Place Marsupilami will start between the Rue Reper-Vreven, Rue Stevens-Delannoy and Rue Félix Sterckx. The works will normally last 80 working days.

Which works?

The development works at the Place Marsupilami will be carried out in 5 phases:

Phase 1:

  • Start: 23 March 2022
  • Duration: 1 day
  • Intention: transplanting the 5 removed trees (see map)

Transplanting the 5 removed trees

Phase 2:

  • Start: 19 April 2022
  • Duration: 15 days
  • Intention: works on the square + sidewalks

Phase 3:

  • Start: mid-May
  • Duration: 50 days
  • Intention: works on the square + sidewalks + roads

Phase 4:

  • Start: August
  • Duration: 25 days
  • Intention: works on the square + sidewalks + roads

Phase 5:

  • Start: November/December 2022
  • Duration: 1 to 2 days
  • Intention: planting new trees

Accessibility?

The passage of pedestrians, cyclists, people with reduced mobility and access to shops and homes is guaranteed throughout the duration of the works.

More info?