Works at the Vismet
Works by utility companies (Sibelga, Vivaqua, Proximus) will take place at the Vismet (Quai aux Briques - Baksteenkaai) from approximately 11 January to 30 May 2021.
Schedule
- From 11 January to 2 April 2021: trenches (with cable laying), laying in sections (access to shops and homes is always guaranteed, terraces are moved as much as possible)
- From 19 April to 30 May 2021: connections (at the choice of the trader/owner)
- Vivaqua intervention: individual connections (1.5/day)
- Proximus intervention (to be determined): laying of fiber optics, no connections in the near future
Map with phases
- Vismet works map (PDF, 794.05 KB)
Phases:
- Phase 1: Quai aux Briques
- Phase 2: Rue du Chien Marin
- Phase 3: crossing Quai aux Briques
- Phase 4: crossing Quai au Bois à Brûler
- Phase 5: Rue du Peuplier
- Phase 6: Quai au Bois à Brûler